Tunnel of Pumped Storage Power Station in Guangdong Huizhou


1 Basic information of project
2 Water quality situation of Huizhou pumped storage power station current situation of diversion tunnel and technical solution
3 Needed equipment, material and method for waterproofing and anticorrosive application

3.1 Trowel coating
3.2 Spray coating (use for large area application)

4 Effect after application (compare with other five test sites used for different waterproofing and anticorrosive materials)
5 Acceptance of works

 


 

Waterproof and Anticorrosive Test Report on Diversion
Tunnel of Pumped Storage Power Station in Guangdong Huizhou


  In order to resolve the waterproof and anticorrosive problem in diversion tunnel of pumped storage power station, at the invitation of headquarters for Guangdong Huizhou pumped storage power station, Zhonghe Waterproof Material Co., Ltd delegated engineering technical personnel LU Hong-jie, CHEN Dong, CHAI Fu-sheng did the waterproof and anticorrosive test in a section of 0# branch tunnel on 24th - 25th January, 2007. This section is ring form with 1.5m wide. The area is 42m2.

ZHONGHE

Address: No.168,Jintang Rood,Hedong District,Tianjin,China

Communication address: P.O.B No.〔7〕77,Tianjin,China

TEL:86-22-84801243

E-mail:zhonghe2000b@163.com

Copyright © 2012 - 2016 ZHONGHE Waterproof Material Co., Ltd All rights reserved.